Faster, lower-cost interconnection by combining ERCOT, MISO, PJM approaches

ERCOT’s approach enables interconnection in 2 to 3 years, whereas recent regional transmission planning by MISO and PJM found cost-saving ways to interconnect 53 GW and 75 GW of renewables respectively, said a Brattle transmission expert.

“What’s so striking” about the amount of renewable generating capacity added across US grid regions last year “is that ERCOT interconnected about 6,000 MW of renewables, while PJM interconnected only about 2,000 MW,” even though PJM is more than twice as large as ERCOT, Johannes Pfeifenberger, a Principal with The Brattle Group said in a presentation.

ERCOT’s process “is so much faster than some of the other processes,” Pfeifenberger said, because ERCOT “pretty much” follows a process known in the UK as “connect and manage,” as opposed to the “invest and connect” approach followed by most US grid operators.

The UK generator interconnection process only considers local upgrades needed to make the injection point “robust enough,” he said, and any network constraints or congestion “are then dealt with through an operational management process like congestion management, curtailment, or network upgrades if planned on a regional basis.”

ERCOT manages network constraints through market dispatch, Pfeifenberger said, “which imposes high congestion and curtailment risks” on interconnecting generators, in part due to “ERCOT’s insufficiently proactive grid planning.”

He believes that generator interconnection that’s “more focused on the local needs will be more timely and cost-effective if combined with proactive regional transmission planning.”

To illustrate that point, Pfeifenberger gave two examples from the MISO and PJM grid regions. MISO has proposed a $10 billion portfolio of six transmission projects that would support interconnection of 53 GW of renewables, and reduce other costs by $37 to $68 billion. PJM identified $3.2 billion in upgrades that would support interconnection of 75 GW of offshore wind, or just $40/kW, which compares to a cost of $6.4 billion PJM previously identified for incremental upgrades for 15 GW of offshore wind.

By being practive about regional transmission planning, Pfeifenberger said, “…you can really speed up the generator interconnection process quite tremendously.”

In a side note, the Mid-Atlantic and Northeast regions are “quite behind in terms of renewable demand versus project development,” he said. Both regions have a large gap between renewables projects at an advanced stage of development, and the renewables targets of the states in those regions, he said, citing a Lawrence Berkeley National Laboratory report.

GOODBYE OLD WAYS

It’s okay to break tradition. Today’s electricity needs are more sophisticated than ever, making traditional power a thing of the past. Switching to solar helps you get with the times while saving the planet.

GREEN CONSCIOUSs

Traditional power has adverse environmental effects from the coal and natural gases combusted during production. Solar offers all of the power with no extra cost and no harmful polutions..

POWERED BY THE SUN

Rather than digging up fossil fuels, solar energy is clean power from the sun - a renewable fuel source that won't go out in our lifetime. Every kW lowers your carbon footprint by over 3K pounds annually.

Share this post

DON’T MISS OUT!
Subscribe To Newsletter
Be the first to get latest updates and exclusive content straight to your email inbox.
Stay Updated
Give it a try, you can unsubscribe anytime.
close-link

Let's Work Together

Complete the form below and we will reach out right away to connect about all of your Solar needs!